The Three Point Estimation technique

Expected \ time = \frac{Optimistic \ estimate \ + \ 4(Most \ likely \ estimate)\ + \ Pessimistic \ estimate}{6}

Example

If an activity has optimistic duration 6 days, pessimistic duration 4 days and most likely duration 5 days then the expected duration is equal to 5 days.